Work from area, not from a block count
Counting blocks directly off a drawing is slow and error-prone. Measuring wall area is fast, checkable by someone else, and converts cleanly into a quantity once you know the blocks-per-square-metre figure for the size and coursing you are using.
The method
- Measure each wall's length and height, and multiply for gross area in square metres
- Group the walls by block size — 4, 6 and 8 inch are separate quantities
- Deduct openings: doors, windows and any large void
- Multiply the net area by the blocks per square metre for that size and coursing
- Add a waste allowance for cutting, breakage and handling
- Round to whole delivery units and set the dates each batch is needed
Do not forget these
- Boundary and perimeter walls, which are often omitted from the building take-off
- Internal partitions and service walls in bathrooms and utility areas
- Gable ends and parapets above the main wall height
- Cutting waste around openings, radii and setting-out points
Turning the quantity into a delivery plan
The total quantity is only half the job. Split it by stage — substructure, ground floor walls, upper floor, partitions, boundary — and give each stage a required date. That is what lets a supplier schedule production and deliver in sequence instead of dropping everything on site at once.